Roscommon Town update

Works on the Roscommon Town Main Drainage Scheme have progressed significantly in the first month of 2023.

Since the new year all the tanks in Wastewater Treatment Plant have been covered with structural screeds progressing, 15m diameter pumpstation is underway in Circular Road in very difficult ground conditions. Plus the installation of the main feeds into the Circular Road Pumpstation is progressing with the dig in excess of 5m depth being supported in poor ground by bottom driven steel piles with a cross member system.

Gallery

click on any of the images to launch gallery

Recent Water Projects from GMC

Sewer Stand Down

Sewer Stand Down July 4th, 2024 In light of a recent incident in Hong Kong where 2 operatives working in a sewer were overcome by Hydrogen Sulphide gas and died,…
Read more

Enfield Key Water Infrastructure Upgrade

Enfield Key Water Infrastructure Upgrade February 15th, 2024 Uisce Éireann’s commitment to supporting future social and economic growth in Meath continues with confirmation that works will commence in the middle…
Read more

The Liffey Siphon

The Liffey Siphon January 25th, 2024 The Liffey Siphon was constructed in circa 1900 as part of the original Dublin City Drainage Scheme that removed untreated wastewater discharges from the…
Read more
Urban Cloudforest maintenance day badge
Proudly Supporting The Urban Cloud Forest Initative
Read more
© Copyright 2017 – 2024 GMC Utilities Group, GMC House, Millennium Business Park, Cappagh Road, Ballycoolin, Dublin 11, Ireland, D11ER02.